  A grid for mpping the probability of occurrence of each impact on project objectives if that risk occurs is used in (71).

  (71)A.risk plan process

  B.risk control process

  D.risk response process

  C.risk analysis process

  Machine leanning a fundamental concept of (72) research since the field ´s inception,is the study of computer algorithms that improve automatically throgh experience.

  (72)A. date center

  B.artificial intelligence

  C.edge computimg

  D.lnternet Protocol Version 6

  The project (73) processes include: develop project charter, develop project management plan,direct and manage project work,manage project knowledge,monitor and control project work,perform integrated change control and close project or phase.

  (73)A.integration management

  B.scope management

  C.schedule management

  D.resource management

  (74)includes the process for incorporating the organization's quality policy regarding planning managing and controlling project and product quality rquirements in order to meet stakeholders’objectives.

  (74)A.Project risk management

  B.Project communication management

  C.Project stakeholder management

  D.Project quality management

  (75)is the process of monitoring the status of the project to update the projects costs and managing changes to the cost baseline.

  (75)A.Control costs

  B.Costs udates

  C.Validate scope

  D.Monitor comnunications